“Crossover” TBM
Completes Mine Tunnels
A ground-breaking TBM brought a mining
operation one step closer to first coal on February 9, 2015. The Robbins Dual Mode “Crossover” Rock/EPB
TBM completed tunneling at Anglo American’s Grosvenor Project in Queensland,
Australia. The “Crossover” designation is new for Robbins Dual Mode TBMs, and
will be used for all such projects going forward. The efficient type of TBM used at Grosvenor
is now known as an XRE, standing for Crossover between Rock/EPB. Other types of
machines are designated the XSE (Crossover between Slurry/EPB) and the XRS (Crossover
between Rock/Slurry).
The Grosvenor Mine, a Greenfield coal
operation, was the first to utilize TBM technology for mining tunnels in
Queensland. Mine owner Anglo American Coal
chose the 8.0 m (26.2 ft) machine for two decline access tunnels at grades of
1:6 and 1:8, one for conveyors and another for people and equipment.
The Robbins Crossover Rock/EPB was launched in December 2013 following Onsite First Time Assembly (OFTA) at the jobsite |
The XRE TBM was picked over the
traditionally-used roadheader method for several reasons, including excavation
speed and tunnel maintenance. The choice proved prescient with the machine
excavating at a rate approximately ten to fourteen times faster than a
roadheader—about 70 m per week for the TBM vs. 5 m per week for a roadheader.
In addition, the final tunnels have a smooth profile and are segment-lined,
requiring minimal upkeep during the planned 40-year life of the mine. “In the
coal mining community, and certainly in Queensland, companies are aware of the
Grosvenor project and how it has set a benchmark for underground access drift
construction,” said Glen Maynard, Robbins Field Service Site Supervisor at
Grosvenor.
Rates of tunneling for the Robbins Crossover TBM were fourteen times faster than that of a traditional roadheader excavation Image: Courtesy of Anglo American |
The machine’s Crossover capabilities
enabled it to operate in both hard rock and mixed ground. In addition, the TBM
was required to operate during gaseous conditions. The unique TBM design included a cutterhead capable
of interchanging hard rock and soft ground cutting tools, a two-stage
center-mounted screw conveyor, a “quick removal” shield system, and flame-proof
machine components due to the possibility of methane gas in the underground
environment.
The TBM was optimized for hard rock and
mixed ground excavation in geology ranging from soft clay and soil to sandstone
and basalt. The two-stage screw conveyor worked in both ground conditions to
draw muck from the tunnel face. Two sets of shields were built for the TBM’s
“Quick Removal” system, and were detached from the machine at the end of each
blind tunnel to be left in the ground for constant support, a requirement in
Australian tunnels. The inner core components of the TBM were then retracted
out of the segment-lined tunnels on specially designed transport dollies.
The machine began boring the conveyor
tunnel in December 2013, and after completion in May 2014 was successfully
retracted and transported to the second tunnel site. The machine was then
re-commissioned for the people and equipment tunnel in November 2014 with a new
set of shields. Once excavation commenced, boring was completed in 88 days at
an average of 10.9 m per day, with a best day of 25.2 m. The bore itself was
similar to the first, with few challenges encountered other than elevated
methane gas levels that required several temporary stoppages in order to safely
remove the gas from the tunnel. “The machine performed very well and had high
reliability. The cutting tools, in particular the knife edge bits, were
exceptional. The bits were required for most of the drive and one complete set
lasted 650 meters,” said Maynard.
The Robbins Crossover Rock/EPB machine completes tunneling on February 9, 2015. Image: Courtesy of Anglo American |
The team is now preparing the machine for
its final retraction and roll-out, and it will be on the surface in less than
two months. The TBM will then be stored
onsite for future Anglo American mining projects.
Workers from owner Anglo American celebrate
the breakthrough of the Robbins Crossover Rock/EPB machine on February 9, 2015.
Image: Courtesy of Anglo American
Once the longwall mine is operational in 2016,
Grosvenor is expected to produce five million tonnes of coal per year over the
next 26 years.
conveyor belting Distributor
ReplyDelete