Robbins Main Beam ramps up at Mid-Halton Outfall Tunnel
On July 22, 2015, a
3.5 m (11.5 ft) Robbins Main Beam TBM began a new chapter in its storied
32-year career. Originally built for the Terror Lake project in Alaska, the
veteran machine has been used all over the world, most recently in Hong
Kong. Including its new 6.3 km (4.0 mi)
long tunnel for the Mid-Halton Outfall in Ontario, Canada, the machine will
have bored nearly 30 km (18.6 mi) of tunnels since 1983.
Officials from the Mid-Halton Region visit the hard-working Robbins Main Beam, nicknamed “Peggie” in the Solon, Ohio, USA manufacturing facility. Photo Credit: Michelle Hill, NASTT. |
The machine’s latest
endeavor will not be without challenges.
The rebuilt TBM has been beefed up for high-capacity tunneling in hard
rock. Geology is expected to consist of laminated shale with interbedded
limestone and siltstone layers and a maximum rock strength of 120 MPa UCS. “We have kept this a simple, streamlined Main
Beam machine, but we modified the cutterhead with larger muck buckets, so
material can be moved through it faster,” explained Robbins Project Manager
Lynne Stanziale. In addition the TBM was
outfitted with fully modernized VFDs, electronics, and high-capacity gearing
and motors. The back-up system was also modified to make it more mobile through
two 130 m (427 ft) radius curves that the TBM will have to navigate, one in
each direction.
“The concept of using
refurbished TBMs bears great opportunities for value-for-money constructors,”
said Christian Zoller, Commercial Project Manager for contractor STRABAG. “Our TBM ‘Peggie’ is evidence of that--when
well-maintained and professionally refurbished, the lifespan of these machines is
extensive. We’re pleased to see that our client Halton Region has the
forward-oriented mindset that allows STRABAG to provide its renowned high level
of skill and quality, paired with the good value for money that a refurbished
TBM yields.”
Contractor STRABAG,
who has had several projects in Canada including the epic Niagara Tunnel
project, is in charge of the works. In
addition to the tunnel, STRABAG had to construct two deep shafts for the launch
and exit of the TBM. The scheme
involves two sections of tunnel designed to carry treated effluent water from a
treatment plant in Oakville into Lake Ontario.
The completed system will upgrade water treatment capacity in the Halton
Region of Ontario.
The Robbins Main Beam TBM has been in service since 1983, and with its new project for the Mid-Halton Outfall, it will have bored nearly 30 km (18.6 mi) of tunnels. |
The TBM was launched
from a 12 m (39 ft) diameter, 62 m (203 ft) deep shaft and is ramping up
production, having excavated over 300 m by early September 2015. “An ongoing challenge
associated with the tunneling on this project is the requirement to drive the
TBM downhill for the first 4 km (2.5 mi) of the tunnel. Keeping the water that
infiltrates the tunnel from flowing directly to the cutterhead requires
significant effort,” said Terry McNulty, Technical Project Manager for STRABAG.
Management of water inflows is not the only
challenge. A portion of the drive will curve to run directly under Lake Ontario
for 2.1 km (1.3 mi), though the tunnel is deep enough that it will remain in bedrock.
Once the machine has completed its final bore under Lake Ontario, it will be
backed out of the blind heading and removed from an 8.0 m (26 ft) diameter
shaft in a local park.
Contractor Strabag lowers the main beam of the Robbins TBM into the 62 m (203 ft) deep launch shaft. |
“We can already see the
potential performance that this TBM will have, once fully assembled and tested.
We look forward to the continued support and cooperation with our partner
Robbins on this endeavor,” said Zoller. Though
the TBM has only recently started up, crews are moving forward with a plan to
line the tunnel with mesh panels and ring beams if necessary. A cast-in-place liner will follow on after
tunneling is completed in August 2017.