Robbins Machine is the first TBM to break through in Two Decades
The 7.4 km (4.6 mi) long headrace tunnel for the Røssåga Hydroelectric Project offered up a number of challenges to the crew. “We bored through hard, quartz-rich rock with rock strengths up to 300 MPa (43,500 psi) UCS and softer karstic limestone with water ingress,” explained Tobias Andersson, TBM Manager for contractor Leonhard Nilsen & Sønner (LNS). Despite the geological challenges, the TBM performed very well and achieved a record production of 250 m (820 ft) advance in one week, as well as a high of 54 m (177 ft) in one day. Advance rates consistently ranged from 180 to 200 m (590 to 660 ft) per week throughout the project.
The hard and abrasive rock required both fine-tuning of the disc cutters and a learning curve with regards to TBM operation. “We overcame the rock by adapting driving parameters to the different geology, cutter wear and vibrations of the machine. We had regular maintenance, but most important of all we got really good at changing the cutters, with times down to 10 minutes per cutter change, which couldn’t have been done without good team work,” said Andersson.
It was the many cutter changes that prompted the close-knit team of LNS and Robbins to look for a better solution. “Extremely hard rock (above 250 MPa/36,300 psi) will always be a great challenge for any cutter. The very special features of the rock encountered combined with the extreme hardness made us go back to the Robbins Cutter Department to develop special cutter rings for the project. These rings increased the cutter life significantly for the project and contributed to the good production,” said Sindre Log, General Manager of Robbins Norway.
A crowd of crew members gathered
to celebrate in front of a newly emerged hard rock TBM on December 10, 2015 in
northern Norway, but their celebration was about more than just a breakthrough.
The 7.2 m (23.6 ft) diameter Robbins
Main Beam machine had traversed incredibly hard rock, water inflows, and more
to become the first TBM in the country to break through in over 20 years.
The LNS and Robbins crew celebrate Norway’s first TBM breakthrough in 23 years at the Røssåga Hydroelectric Project. Photo credit: LNS |
The 7.4 km (4.6 mi) long headrace tunnel for the Røssåga Hydroelectric Project offered up a number of challenges to the crew. “We bored through hard, quartz-rich rock with rock strengths up to 300 MPa (43,500 psi) UCS and softer karstic limestone with water ingress,” explained Tobias Andersson, TBM Manager for contractor Leonhard Nilsen & Sønner (LNS). Despite the geological challenges, the TBM performed very well and achieved a record production of 250 m (820 ft) advance in one week, as well as a high of 54 m (177 ft) in one day. Advance rates consistently ranged from 180 to 200 m (590 to 660 ft) per week throughout the project.
The hard and abrasive rock required both fine-tuning of the disc cutters and a learning curve with regards to TBM operation. “We overcame the rock by adapting driving parameters to the different geology, cutter wear and vibrations of the machine. We had regular maintenance, but most important of all we got really good at changing the cutters, with times down to 10 minutes per cutter change, which couldn’t have been done without good team work,” said Andersson.
It was the many cutter changes that prompted the close-knit team of LNS and Robbins to look for a better solution. “Extremely hard rock (above 250 MPa/36,300 psi) will always be a great challenge for any cutter. The very special features of the rock encountered combined with the extreme hardness made us go back to the Robbins Cutter Department to develop special cutter rings for the project. These rings increased the cutter life significantly for the project and contributed to the good production,” said Sindre Log, General Manager of Robbins Norway.
Kare Solhaug of Robbins Field
Service stands proudly in front of the 7.2 m (23.6 ft) diameter TBM on the day
of its breakthrough December 10, 2015. Photo
credit: LNS
|
Robbins Main Beam machine was launched in
January 2014 and overcame incredibly hard rock, water inflows, and more. Photo credit: Statkraft |
The Robbins TBM was launched
following Onsite First Time Assembly (OFTA) in January 2014, less than twelve
months after contract signing, and was from the outset designed for hard rock
conditions. A Measurement While Drilling (MWD) system was included to analyze
the ground conditions ahead of the TBM, while probe drilling was done
systematically throughout the project. “This is a strong and simple machine
ready to tackle hard rock conditions, but also designed to handle softer rock,
which allowed for fast excavation. We had good support from competent Robbins
field service,” said Andersson.
After all the obstacles, it was clear that the breakthrough ceremony celebrated a triumph of teamwork as well as a new chapter for TBMs in Norway. “Our whole jobsite was gathered for the event: LNS management, representatives from Robbins, and our client Statkraft. People said it was the best breakthrough event they had seen,” said Andersson. Now that tunneling is complete, project owner Statkraft will work to commission the tunnel and fill it with water by spring 2016.
After all the obstacles, it was clear that the breakthrough ceremony celebrated a triumph of teamwork as well as a new chapter for TBMs in Norway. “Our whole jobsite was gathered for the event: LNS management, representatives from Robbins, and our client Statkraft. People said it was the best breakthrough event they had seen,” said Andersson. Now that tunneling is complete, project owner Statkraft will work to commission the tunnel and fill it with water by spring 2016.